Pekat secures RM62.91 million in Port Dickson data centre work
Four subcontracts awarded to Pekat E&LP cover earthing and lightning protection, with completion scheduled in stages during 2028 and 2029.

Pekat Group Bhd has won four subcontracts totalling RM62.91 million for a hyperscale data centre in Port Dickson, Negri Sembilan, according to its filing with Bursa Malaysia. The work involves earthing and lightning protection at the project.
The recipient is Pekat E&LP Sdn Bhd, a subsidiary of the group. A Malaysian engineering and construction company awarded the subcontracts, but Pekat said confidentiality obligations prevented it from identifying the company. The scope includes building, completing, testing and commissioning the protection systems, as well as related work.
The individual awards are valued at RM19.73 million, RM14.62 million, RM14.49 million and RM14.07 million. Completion is scheduled in stages starting on Jan 21, 2028, while the last subcontract has a target completion date of Jan 5, 2029.
Pekat expects the contracts to support revenue and earnings during their respective terms. For the financial year ending Dec 31, 2026, it does not anticipate a material effect on gearing, net assets or net assets per share.