Thaco Agri and HAGL add industrial projects to agricultural expansion

Projects in Vietnam’s Gia Lai province include the 74.5-hectare Mang Yang No. 2 cluster and the planned 75-hectare Ham Rong development.

By Nadia Hassan

Agricultural fields and industrial buildings in a rural landscape
Photo: The Investor

Thaco Agri and Hoang Anh Gia Lai (HAGL) are extending their agricultural businesses into industrial infrastructure in Vietnam’s Gia Lai province, alongside further plantation investment. Their projects include industrial clusters intended to accommodate processing and other agriculture-related manufacturing.

Work on HAGL’s Mang Yang No. 2 project started in August 2026. The development covers 74.5 hectares, carries an investment of ₫400 billion and has an expected completion period of 30 months. Planned uses include processing farm and forestry output, making export-packaging supplies and producing fertilisers from agricultural by-products.

HAGL’s board has also authorised the establishment of HRA Technical Infrastructure Construction and Business Co., Ltd. The proposed subsidiary would have charter capital of ₫60 billion, funded entirely through a cash contribution from HAGL, and would invest in industrial cluster infrastructure.

For Thaco Agri, subsidiary Thagri Gia Lai Agriculture Co., Ltd. is developing Ham Rong. A provincial government decision puts its area at 75 hectares and estimated investment at ₫1.1 trillion. Operations are expected to begin in the second quarter of 2028, following construction. The investor will provide ₫550 billion, while bank borrowing is expected to fund the balance.

The industrial developments accompany wider farming plans. At its 2027 Strategic Partners Conference, Thaco Agri outlined investment exceeding ₫5.47 trillion for 2027. Its targets include exporting 680,000 tons of bananas and increasing breeding and beef cattle numbers to 200,000 head.

HAGL, meanwhile, set out plans in its November 17, 2026 board resolution to add 5,000 hectares of coffee during 2027, at an estimated cost of ₫3.05 trillion. It aims to finish a coffee-planting programme covering 20,000 hectares by 2028.