Ho Chi Minh City shifts funding as public investment spending accelerates

Disbursement reached 80.1% of the city’s 2026 target by late October, compared with 56.2% at the same stage in 2025.

By Nadia Hassan

Urban road construction with barriers and machinery
Photo: Nhan Dan

Ho Chi Minh City’s public investment spending reached ₫118.278 trillion by the end of October, against a 2026 allocation of ₫147.599 trillion. Authorities are redirecting funds from slow-moving projects and tackling compensation disputes to accelerate implementation.

Eight internal reallocations have involved more than ₫45 trillion, said Hoang Vu Thanh, Director of the Ho Chi Minh City Department of Finance. The approach moves money towards projects better placed to use it, rather than leaving funding tied to delayed work.

Land clearance remains a focus. Authorities are working to hand over about 22,000 square metres needed for the Luong Dinh Cua Road expansion, where compensation problems have persisted for more than 10 years. Binh Trung Ward officials have held more direct discussions with residents and examined petitions individually.

Infrastructure work includes Metro Line 2, where five stations out of 11 were under construction as of October and geological surveying had completed 506 boreholes. The Ho Chi Minh City Urban Railway Management Board put cumulative disbursement at about ₫6.6 trillion on October 22, nearly 88% of the adjusted 2026 allocation.

The city’s December 31 goal is to spend more than 100% of its allocated capital. It is also weighing additional funding for units able to disburse quickly, with a view to reaching 110% of the annual target.