WCE Holdings quarterly loss widens as expressway construction costs rise
Quarterly revenue edged up to RM154.8 million, while the group targets early 2027 for the entire West Coast Expressway to become operational.

WCE Holdings Bhd’s second-quarter net loss increased to RM41.73 million from RM26.4 million a year earlier. The Malaysian expressway group linked the weaker result for the period ending September 30, 2026, mainly to the cost of speeding up construction on Section 7B.
Higher toll receipts from operating stretches helped quarterly revenue reach RM154.8 million, compared with RM154.3 million a year before. Across the six months ending September 30, 2026, losses totalled RM66.22 million versus RM51.72 million previously. Revenue dropped 46 per cent as construction contributed less with the project nearing completion.
For the concession business, a nine per cent increase in toll revenue helped reduce the six-month pre-tax loss from RM67.1 million to RM65.2 million. The construction business reported pre-tax losses of RM15.3 million over the quarter and RM15.1 million over six months, with faster building work, rising material and fuel costs, and design changes weighing on performance.
Construction revenue nevertheless grew 24 per cent for the quarter and 15 per cent over six months. The group attributed those increases to more intensive work on Section 7B and four remaining rest and service areas.
According to WCE Holdings, eight sections are operating, out of 11, covering 180km across Selangor and Perak. Building work continues on Sections 3 and 7. The completed Section 4 is due to begin operations alongside Section 3.
The group aims to bring the whole expressway into operation in early 2027. It expects completion to help increase traffic and recurring toll receipts. Chief executive officer Lyndon Alfred Felix said toll revenue growth reflected improving traffic momentum on the operating sections.