Indonesia’s PT Perusahaan Gas Negara (Persero) Tbk (PGN) said six initiatives under its 2026 programme would develop energy infrastructure and broaden its natural gas market. Capital expenditure reached US$151 million by September 2026, against an annual allocation of US$353 million.

PGN said downstream development and related infrastructure would receive most of the budget. Corporate Secretary Fajriyah Usman said customer needs, economic considerations and the readiness of projects guided investment decisions.

Household connections are one focus. PGN’s jargas programme aims to reach 50,000 potential household connections in seven provinces and 11 cities during 2026. By September, it had built 280 kilometres of pipelines with the potential to serve 36,401 households.

A separate customer attachment programme extends distribution networks through 10 provinces and 17 cities. PGN allocated US$21.74 million to it for 2026 and had spent US$11.29 million by September. The company anticipates potential additional gas sales of 30.57 BBTUD.

In East Java, a flat-bottom LNG storage tank facility at Teluk Lamong is planned for 30 BBTUD. Construction was 0.9 per cent complete in September 2026; PGN aims to commission it in the second quarter of 2028.

The New West Java Regasification project would support a capacity increase of up to 500 MMSCFD. An interconnection pipeline measuring approximately 28 kilometres would connect Jakarta Bay with Muara Bekasi. PGN targets an operational start in the third quarter of 2028.

At Pagardewa in South Sumatra, work on a biomethane injection facility had reached 76.6 per cent by September 2026. Designed for 1.2 BBTUD, it is targeted for commissioning in the first quarter of 2027.

Subsidiary PT Pertamina Gas (Pertagas) is constructing the Cikampek-Plumpang oil pipeline in West Java. The 96-kilometre link is planned to carry 79,800 barrels of oil per day (BOPD). It was 64.6 per cent complete in September 2026, with commissioning scheduled for the third quarter of 2027.